An as-built survey, also called an as-constructed survey, records the location and levels of completed construction works. It provides a record of the completed works for project handover and future reference.
For civil construction and infrastructure projects in the Northern Territory, as-built surveys cover a range of completed works, including roads, drainage, earthworks and structures.
What Does an As-Built Survey Include?
Depending on the works, an as-built survey records:
- Finished surface levels
- Road and pavement levels
- Kerbs and drainage structures
- Pipes and pits
- Building slabs and foundations
- Earthworks and other constructed features
Survey data can be supplied as drawings, plans or digital files, depending on the project requirements.
Why Are As-Built Surveys Important?

Construction drawings show what was planned. An as-built survey documents the actual position and levels of the completed works.
This information is used to:
- Check completed works against the design
- Provide records for project handover
- Support future maintenance or construction
For underground works, surveying pipes and services before they are covered provides a record of their location for future reference.
When Is an As-Built Survey Carried Out?
As-built surveys take place at different stages of construction.
Underground drainage, pipes and other services are usually surveyed before they are covered. Roads, kerbs and finished surfaces are surveyed once the relevant construction stage is complete.
Construction Set-Out and As-Built Surveys
Construction set-out establishes where the proposed works are to be built, using the approved design. An as-built survey records where those works were actually constructed.
Set-out comes first on most jobs. For an example of why, see Pouring a Slab in Darwin? Why the Setout Hold Point Comes First.
Territory Surveys provides as-built surveys, engineering surveys and construction set-out for civil construction and infrastructure projects across the Northern Territory.
Need an as-built survey before handover? Talk to our team.